Flagship project Fonet Er-Tai

Er-Tai Site Engineering Systems

Complete installation of engineering systems and construction and installation works for the hydrometallurgical plant site.

ABLProject dossier
7

fan units

  • Ventilation
  • Heating
  • Climate
2025
Industry
Hydrometallurgy
Period
2025
Geography
Ekibastuz district, Pavlodar region.
Fan equipment
7 units

Object task

What needed to be done

Equip the site with ventilation, heating and climate control equipment and carry out the complex of construction and installation works provided for in the project.

ABL Area of Responsibility

What was done at the site

4 workstreams
  1. 01

    7 VR 85-77 fan units in four standard sizes.

  2. 02

    Mounting frames, vibration isolators, flexible inserts, casings and control cabinets.

  3. 03

    Water air heaters and electric fan heaters.

  4. 04

    Three sets of ALMACOM climatic equipment.

Project scope

A single contract package combined construction and installation work and the supply of equipment for ventilation, heating and climate systems of the site.