Flagship project Temirtau Kazmekhanomontazh No. 2 LLP

10 years of industrial subcontracting

22 contracts and DS for 10 years: ventilation, engineering networks, thermal insulation and equipment for industrial facilities.

ABLProject dossier
22

agreements and DS in the cooperation program

  • Ventilation
  • Utility networks
  • Thermal insulation
2016–2025
Format
Industrial subcontracting
Period
2016–2025
Geography
Kazakhstan
Scale of cooperation
22 agreements and DS

Cooperation format

Industrial subcontracting at different sites

Perform industrial subcontracting at various production sites - from individual engineering systems to complex supply and installation of equipment.

Completed stages

What is included in the cooperation program

4 key stages
  1. 01

    Installation of ventilation for a warehouse of crushed ore and finished products.

  2. 02

    Heating, ventilation, water supply and sewerage systems for activated carbon production.

  3. 03

    Industrial thermal insulation at the Aksu ferroalloy plant.

  4. 04

    Construction and installation work and equipment for the Er-Tai hydrometallurgical plant site.

Project Development

Key Milestones

  1. 2017

    Crushed ore warehouse

    Installation of a ventilation system at a facility in the area of the Kok-John and Gimmelfarbskoye deposits.

  2. 2018

    Production of activated carbon

    Installation of air conditioning and air conditioning systems in Nurinskoye area.

  3. 2019

    Aksu-1

    Installation of thermal insulation with a protective covering layer.

  4. 2025

    Er-Tai

    Construction and installation work and provision of engineering equipment for the hydrometallurgical plant site.

Project scope

22 contracts and DS for 2016–2025 - long-term industrial subcontracting at several sites in Kazakhstan.