Project objective
What needed to be done
Gradually develop the engineering systems of the industrial building: install ventilation and smoke removal, then increase the cooling of the supply air.
ABL Area of Responsibility
What ABL has accomplished
-
01
Installation of ventilation equipment, air ducts and mounting structures.
-
02
Installation of ventilation and smoke removal systems.
-
03
Additional cooling sections in units P1 and P5.
-
04
About 120 m of cold glycol pipeline with thermal insulation and protective coating.
Project Development
Key Milestones
-
2019
Installation of ventilation
Equipment, air ducts and related installation structures.
-
2022
Ventilation and smoke removal
Individual stages of installation of engineering systems of a production facility.
-
2023
Modernization cooling
Sections P1 and P5, mixing units, control and cold glycol pipeline.